Portfolio Milestone Planner

Run the Portfolio Milestone Planner MicroSim Fullscreen
Edit in the p5.js Editor

About This MicroSim

Chapter 25 orders the capstone into seven milestones over a suggested 8-week schedule: Plan, Specify and generate, Instrument, Test and review, Protect, Evaluate and Present. Each milestone has a deliverable and a gate it must pass before the next stage can rely on it. This planner draws the milestones as bars on a week grid, one after another, and lets you fit the plan to your own portfolio.

Three stages depend on the size of the portfolio:

Stage What stretches it Illustrative estimate
Specify and generate Number of MicroSims 0.4 week per MicroSim
Instrument Number of MicroSims 0.2 week per MicroSim
Test and review Test participants and MicroSims 0.25 week + 0.15 per participant + 0.06 per MicroSim

The other four stages stay at one week each. With the defaults (5 MicroSims, 3 participants) the plan reproduces the chapter's suggested 8 weeks. These durations are illustrative planning estimates chosen to reproduce that schedule, not measured effort data; use them to reason about trade-offs, then replace them with your own estimates.

A bar turns amber, with a dashed outline and an exclamation mark, when it would finish after the last available week (the dashed deadline line), or when its gate is at risk for another reason: the project brief asks for three or more test participants. Click a bar to read its deliverable, its gate, how its length was estimated and, for an amber bar, a one-sentence warning.

Learning objective: The learner will design a week-by-week schedule for their own portfolio and identify which milestone gates put the schedule at risk.

Bloom's taxonomy level: Create (verb: design)

How to Use

  1. Set Weeks available to the length of your own course project.
  2. Set Number of MicroSims and Test participants to the portfolio you intend to build.
  3. Read the summary line under the chart: it states the weeks needed and names every milestone that finishes after the deadline or has a gate at risk.
  4. Click any bar, or Tab to the chart and use the arrow keys, to see its deliverable, gate, estimate and warning.
  5. Adjust the sliders until no bar is amber, then press Reset to suggested schedule to compare your plan with the chapter's suggestion.

Iframe Embed Code

You can add this MicroSim to any web page by adding this to your HTML:

1
2
3
4
<iframe src="https://dmccreary.github.io/microsims/sims/portfolio-milestone-planner/main.html"
        height="682px"
        width="100%"
        scrolling="no"></iframe>

Lesson Plan

Audience

Teachers, instructional designers, learning-technology developers and learning-analytics practitioners (college undergraduate and professional development).

Duration

20-30 minutes

Prerequisites

  • The capstone project brief, milestones and gates in Chapter 25
  • The quality gate (Chapter 13) and the instrumentation check (Chapter 17)

Activities

  1. Explore (5 min): Move each slider from one end to the other. Record which bars change length and which only move.
  2. Design (10 min): Enter your real constraints (weeks, MicroSims, participants). Produce a schedule with no amber bars and write it down week by week, with each gate on the week it must pass.
  3. Stress test (5 min): Take one week away. Name the gate that first falls past the deadline and decide what you would cut: a MicroSim, a participant, or scope inside a stage.
  4. Critique the model (5 min): The estimates are illustrative. Write which one you think is most wrong for your own situation, and what you would measure to replace it.

Assessment

  • The learner's final schedule fits the available weeks and meets the brief's minimums (4 to 6 MicroSims of at least three types, 3 or more test participants).
  • The learner names the gate most at risk in their plan and gives a concrete mitigation.
  • The learner states that the durations are estimates and says how they would check them.

References

  1. Gantt chart - Wikipedia. The bar-on-timeline format used by the planner.
  2. Phase-gate process - Wikipedia. Stages that must pass a gate before the next stage begins.
  3. Usability testing - Wikipedia. Background on the test-and-review milestone.
  4. createSlider() - p5.js reference. The slider controls used here.